SASM News Details

Ricardo Road Pump Station Improvements

The Ricardo Road Pump Station Improvements Project is underway and 6% complete..

•The rehabilitation of the Ricardo Road Pump Station including required demolition of the existing pump station, demolition and removal of a 550-gal diesel underground storage tank, generator and controls, including modifications to the existing subsurface concrete structure, construction of a valve pit, a six (6) ft diameter PVC lined influent manhole, installation of a new motor control center and all electrical work, installation of a 125 kW engine generator, all surface improvements, site improvements, fencing, landscaping, irrigation, drainage improvements, pavement restoration, temporary controls, bypass pumping, a 12 inch line stop, including demolition and removal of a 550-gal diesel underground storage tank at the Salt Works Pump Station, relocation and installation of a 300-gal day tank and fill port from the Ricardo Road Pump Station to the Salt Works Pump Station, demolition and disposal of a 225 kW turbine generator set from the Trestle Glen Pump Station. 
•Pacific Infrastructure Corporation (PIC) was the lowest responsible bid of $2,223,500 and issued Notice of Award on 3/22/2019.  
•Notice to Proceed was issued on 5/1/2019.  Contract allows the contractor 210 calendar days from NTP, resulting in a completion date of 11/27/2019.   
•Contractor’s submittal and ordering process is completed.  Site has been cleared and bypass pumping, pump back-up and alarm system is being set-up prior to building demolition.  
•New pump station is scheduled to be completed and fully operational by 11/27/2019.